Currently waiting on the circuit boards - there has been a shortage of one of the components since an order of 200 that got damaged in the post.
Hopefully i should get the first six boards in the next 2-3 weeks, and then the remainder shortly after.
Therefore what i shall probably do is release the first 6 ( I shall build everything ready waiting on these boards) when these arrive, and then as soon as the rest arrive a couple of weeks after i shall send the rest out.
Therefore realistic timescales are looking around the middle to end of November.
Thanks for the update. This year I'm getting a Christmas present I actually want. Looking forward to the 'where I put my DMD clock thread for Christmas. The rest of my presents will be put in the sock drawer
Had confirmation that the first of the new set of boards (QTY6) will be in with Limpan on Nov 5/6th, so should be with me within a week of this date. Will be ready to rock and roll here with frames all built and ready to go - if all goes well will be ready to ship within 2-3 days of these arriving with me. Will ship in order that they appear in the list above....
Once these are shipped then i will just be waiting on the final 10 or so boards to arrive, which Limpan advises should be around when i have completed the first lot
Chris - Key issue is the frames. Let me do a final check of how many i need and how many i have, and get back to you
Aim is to get everyone sorted on this before the start of December...
Boards already ordered, so as soon as those arrive I'll be working on them to get them out asap (have all the rest of the stuff needed waiting!). Looking at 2-3 weeks all being well
Awaiting the last 3 boards. Also noticed i was some led panels short (my fault - apologies - miscounted). So remaining panels on their way - should be here by the end of the week.
There is a slight problem in that i have to go away for work (no choice) this week, so will try to get a few completed this weekend and out Monday, and then will take just over a week to get the others (as need to wait for the deliveries - and as i'm not here to pay customs charges could prove interesting...).
Either way, looking to get some sent Monday, and then the remainder around the 15th if all dates line up.
Unless something disastrous happens (and that would be VERY unforeseen!) - these will ALL be with you for christmas